2:22 Community member concerned about data centre proposed on UNESCO geopark RELATED: Community member concerned about data centre proposed on UNESCO geopark – Jul 14, 2026A New Brunswick member of Parliament is calling on the provincial government to reject a proposed artificial intelligence data centre in Saint John, warning that it could overwhelm the power grid.
Conservative MP John Williamson says the proposed AI centre will trigger electricity rate hikes for nearby residents.
Williamson says the public utility NB Power lacks the necessary capacity to handle the facility’s demand for 200 megawatts from the grid.
He laid out his opposition to Beacon Data Centers’ project in a letter to Liberal Premier Susan Holt.
2:07 Saint John, Lorneville residents protest data centreThe New Brunswick Southwest MP also criticized Holt for highlighting the data centre project at a major Toronto investment summit earlier this week, even though it hasn’t received provincial government approval.
- Uncertainty hangs over Nackawic after pulp mill announces temporary shutdown
- This invasive species has just been found in Canada for the 1st time
- Nova Scotia to mark 52 historic African Nova Scotian communities with new signs
- Conservative MP Larry Brock officially resigns from House of Commons
The New Brunswick government says any new data centre must pay for the costs it creates and cannot lead to higher electricity rates.
Get breaking National news
Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story. By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.Beacon AI says its project requires 390 megawatts of energy and that it could produce up to 190 megawatts on site.
Williamson said the company wasn’t interested in generating all of its own power.
“I met with them and I raised this and they balked,” he told The Canadian Press in an interview Friday, referencing a meeting he had with the company a several months ago.
That’s why, he said, he wants the province “playing hardball” with companies that want to build data centres so that ratepayers are shielded from major price hikes.